If you have driven by the new elementary school, you have noticed landscaping is well underway, with all asphalt scheduled to complete by June 23. Additionally, the grass sod will complete the first week of July. The Utah State Fire Marshall will also complete his inspections on July 3. After we receive approval from the State Fire Marshall, we can begin moving curriculum materials and library resources in preparation for the start of school in August 2023. The district has purchased new tables, student desks, and furniture for the entire building. We will plan an open house for the public on August 7, where we will have a ribbon-cutting ceremony, then anxiously await the first day of school in the new building, which will be August 15.