I’d like to provide an update on the progress of the construction of the New Kanab Elementary School. The construction site currently has 40 workers assigned to the project this week; the following is a detailed list of the work completed, in progress, and planned.
Work Completed:
Underground on-site utilities – water main, fireline, fire hydrants, storm drain, sewer
Perimeter footings – Areas “A”, “B”, “C” & “D”
Parking lot grades cut to sub-grade on west and north side of the building
Primary electrical feeds completed to all electrical rooms and data rooms
Underground plumbing completed – Areas “A”, “B”, “C” & “D”
Excavated footings – maintenance building
Building slab floor – classrooms
Stage retaining walls
Stage floor slab
Kitchen floor – Slab
All bathroom floors
Common area and hallway floors
Underground electrical – primary from building to offsite tie in
Underground electrical conduits at the maintenance building for transformer and CT cabinet
In progress:
Storm drain – off-site
Sewer – off-site
Off-site curb and gutter prep – Powell Dr., Kanab Creek Dr., Vermillion Dr.
Strip forms building slab
Parking lot lighting conduits
Floor cleaning/Buffing – Prep for concrete wall panels
Maintenance building footings
Work planned:
Complete cleaning floors in preparation for wall panel casting
Maintenance building footings
Landscaping PRV and backflow manifold in the maintenance building
Form and cast wall panels – maintenance building and area “A”
Mobilize crane onto site – week 1 of November
Stand wall panels – Maintenance building and area “A” – will take place right after the crane arrives on site
Decking and joist scheduled to arrive in October. Steelwork will begin as soon as panels are erected
All trades will follow behind deck and joist to install their infrastructure for the building
Pour/Slip with curb machine off-site curb and gutter – working to finalize a date
A few important dates to look forward to, the mobile crane used to lift walls in place will be on-site the first week of November at which point they will begin to stand the walls. We are excited about the progress of the new school and look forward to its completion. If you have any questions, you are welcome to come into the district office anytime. I’d like to thank all the neighbors for putting up with the traffic, noise, and lights. Your patience is appreciated!